Guide
Controlled shipping: how it starts, what to require, and how a supplier gets released
The short answer. Controlled shipping is a customer-imposed regime in which a supplier adds a checking step, often a 100% sort, so that suspect parts cannot reach the customer while the cause is fixed. Many customers use two levels: the supplier sorts and reports at Level 1, and a third party is added at the supplier’s cost at Level 2. The triggers, labels and exit tests are set by each customer, so the useful work is writing yours down: what starts it, what you require, and what evidence ends it.
Where it sits in the problem-solving chain
ASQ describes the eight disciplines (8D) as a problem-solving model, common in the auto industry, whose third step is to develop and execute an interim containment plan that isolates the problem, and whose sixth is to implement corrective actions and verify they work. Controlled shipping is what a customer adds when it does not trust the supplier’s containment to be enough on its own: the interim step becomes formal, observed and escalating.
That framing helps with one common confusion. Controlled shipping is not a penalty and not a corrective action. It is containment under supervision, and it only ends once the corrective action has been shown to hold.
What three customers actually write down
We read three published rules. They are one company’s policy each and are not an industry benchmark, but the contrast is useful because it shows which parts are common and which are a choice.
| Adient (Quality manual, Rev 7.0, 1 Feb 2022) | Nexteer (Containment Instruction, revised 20 Dec 2022) | Mann+Hummel (CSL instructions, April 2014) | |
|---|---|---|---|
| What starts Level 1 | Adient identifies a supplier quality issue and sends a Level 1 notification | Judged on repeat problems, duration and severity, incapable processes, customer issues, inadequate containment, major disruption; Nexteer must first agree internally that current controls cannot protect it | Supplier notified in writing; must return it signed within 24 hours |
| First clock | Initial 8D containment plan within 24 hours | Reply to the notification letter; extra inspection with a reaction process | Start an 8D and confirm it to the plant quality contact within 24 hours |
| What Level 1 requires | Quarantine and sort suspect product at the supplier, sub-contractors, in transit, at Adient sites and at customer locations; report daily | Sort at the supplier plant, post results on information boards, management review at least once per shift, label outgoing material | 100% containment, shipments labelled CSL 1; unlabelled shipments are inspected at the customer at the supplier’s expense |
| What starts Level 2 | Level 1 fails to stop nonconforming material reaching Adient or its customers | Level 2 adds a third-party inspection on top of Level 1 | Not stated in the pages we read; shipments labelled CSL 2, and may also carry the CSL 1 label |
| Who pays | Supplier pays Adient’s costs for Level 1 and all sort-company costs at Level 2 | Supplier pays all third-party inspection costs | Stated only for unlabelled shipments: the supplier |
| How it ends | Exit criteria set by Adient quality as a quality level to be reached, not parts sorted or days elapsed; at least 30 days, or another period Adient specifies | Measurable criteria specific to the nonconformance; run chart showing zero defects, verified root cause, evidence the actions work; formal exit letter | Root cause confirmed, actions implemented including on similar products, no recurrence for at least 1 month or 3 production batches, documents updated, written approval |
What the three have in common
- A short acknowledgement clock, 24 hours in two of the three, which tells the supplier the customer treats it as urgent.
- Containment that covers every place suspect stock can be, not only the supplier’s own warehouse. Adient names five locations.
- The supplier carries the cost, and Level 2 means paying for an independent party.
- An exit decided by a named quality contact at the customer, not by the supplier. Nobody exits by default.
Where they differ, and why it matters to you
The exit tests are the real difference. Adient ties release to reaching a quality level and treats time as a minimum, not as the measure. Mann+Hummel in 2014 counted a period or a number of production batches. Nexteer asks for a run chart of zero defects and leaves the duration to the supplier quality engineer. If you are writing your own rule, the lesson is that a duration alone is the weakest of the three, because it lets a supplier wait out the clock without proving anything.
A buyer’s checklist for the decision to start
This is our own method, offered as a starting point. Answer these before you issue a notification, and keep the answers with the record.
- Did containment fail, or is it absent? Level 1 is a response to a problem that needs supervised containment. Level 2 is for the case where Level 1 did not stop escapes. Skipping straight to Level 2 should be a recorded decision with a reason.
- Is it a repeat? Same part, same characteristic, same cause family. A repeat is the strongest signal that the earlier corrective action did not work.
- How severe is the escape? What reached your line or your customer, and what would have happened if it had not been caught?
- Where can suspect stock be? List the supplier, sub-tier, in transit, your sites, your customers and your customers’ sites. Anywhere you cannot see is where a second escape comes from.
- Who decides, and who can lift it? Name one person at your end for each, and say so in the notification.
What to put in the notification
- The part numbers and the defect, described so a stranger could inspect for it.
- The level, the reason it starts at that level, and the date.
- The acknowledgement deadline, the containment plan deadline and the reporting frequency.
- How shipments must be identified, and what happens to unidentified ones.
- The exit criteria, in writing, at the start: the evidence you will accept, the minimum period or number of batches if you use one, and who signs the release.
An illustrative record
The numbers below are invented, to show the shape of the record and not typical values.
| Field | Example entry |
|---|---|
| Part and defect | Bracket 4471-B, burr on the 12 mm bore above the drawing limit |
| Trigger | Third escape in six weeks; earlier corrective action found not effective |
| Level and date | Level 1, notified Monday; Level 2 not applied, reason recorded |
| Acknowledged, containment plan in | Within 24 hours, within 24 hours |
| Locations contained | Supplier plant, one sub-tier, goods in transit, our two plants, one customer site |
| Daily result | Lots sorted, pieces checked, defects found, defect type |
| Exit criteria set at the start | Root cause verified; corrective action in place; no defect of this type across 10 consecutive lots and at least 30 days; control plan updated |
| Release | Written, signed by the named quality owner, with the evidence attached |
What this does not do
- It does not fix the cause. A sorted lot is a good lot; the process that made the bad one is unchanged until the corrective action lands.
- It does not replace a conversation. A supplier on controlled shipping is often one with a capacity or process problem, and the data from the sort is the most useful thing you will get about it.
- It does not apply to every customer relationship. If your own contracts do not give you the right to impose it, start by reading them.
How EvaluationsHub fits
EvaluationsHub keeps the corrective action, the evidence and the decision in one supplier record, so the question “can we release this supplier?” is answered from documents rather than from memory. Eva AI Agent works in the background and finds gaps between what a supplier committed to and the record on its own, and when a gap crosses a defined threshold it generates the corrective action with its reasoning attached. A person approves, edits or dismisses it before anything reaches the supplier. We do not describe a dedicated controlled shipping feature here, and we have not tested the rules above in the product.
What we cannot tell you
- What your customer’s manual requires of you. Read it; the rules above differ from one another on purpose.
- Whether a given exit threshold is right for your part. The 10 lots and 30 days in the example are invented.
- What ISO 9001:2026 changes for nonconforming output. We have not read its text.
- How other companies’ rules read today. The Mann+Hummel document we used is from 2014 and may have been replaced.
Questions people ask
Is controlled shipping defined in an international standard?
We did not find one. The terms and thresholds we read come from individual customers’ supplier manuals, so the rules that bind you are the ones in your customer’s document. The problem-solving method it usually sits inside, 8D, is described by ASQ as a model with eight steps, including interim containment and validation of corrective actions.
How is it different from containment in an 8D?
Containment in 8D is the supplier’s own interim action to protect the customer while the cause is unknown. Controlled shipping is the customer making that containment formal, adding reporting, labelling, cost allocation and an exit gate. The same logic applies: containment stays until the corrective action is shown to work.
Does the buyer need a record of this under ISO 9001?
Under the 2015 edition, clause 8.7 requires outputs that do not conform to be identified and controlled to prevent unintended use or delivery, and documented information on the nonconformity, the actions taken, any concessions and who decided. We read that through training providers’ summaries, because the standard itself is paywalled. ISO 9001:2026 has since been published and we have not read its text.
Should the exit criteria be written at the start?
Yes, in our view. All three policies above put the release decision with a named quality contact, and one requires criteria that are measurable and specific to the nonconformance. A criterion written on day one is a lot harder to dispute on day sixty than one invented at the end.
See a supplier record with its corrective actions
Send us how you evaluate suppliers today and we will rebuild it in your own environment inside 48 hours.
Request a pilot environmentSee it workingGet a price for my situation